Bayview Retirement Community

Preconstruction Success

COMPREHENSIVE 6-MONTH Preconstruction 
PROCESS FOR THIS complex phased renovation

Extensive planning was essential to safely plan for an addition and renovations on every floor of this fully occupied 10-story retirement community.

Bayview Retirement construction render

Disruption Avoidance Planning for Ongoing Operations


To ensure residents could go about their daily activities without disruption, our team worked closely with the owner and design team on a phased plan to keep the facility 100% operational throughout 20 months of construction.

Mitigating unforeseen conditions


Remodels present unique challenges related to the unknowns prior to construction. Thorough review of all scope items with subcontractors uncovers potential risks, that can then be addressed prior to construction.

Mounting an Anderson Construction logo on a crane

Our integrated, team approach starts from day one. We engage with the design partner and critical subcontractors early and often.

20 months

4 distinct phases

Gathering in Bayview Retirement Community

Proactive & Ongoing communication


Our comprehensive preconstruction approach sets up the plan and approach for construction activities. These are communicated in person to ensure all residents know of upcoming events. 

bayview-image.jpg

Utilizing Technology to Minimize Risks


Modeling the new structure in 3D allows our team to foresee and resolve constructability issues without affecting the schedule or budget.

150 residents

Construction workers laying concrete

"Andersen Construction is performing great on our project. They were a valuable team player during pre-construction; thinking creatively on how to achieve our goals and meet our budget. We are currently under construction in an occupied building, which has its challenges and surprises. Andersen is pro-active in resolving Issues. They handle everything with a positive attitude and promptly."


Julie Lawton

Lawton Project Management Group