A unique enterprise team structure of design (BCRA Architects), construction and key trade partners was established to ensure consistency and quality while maintaining the fast-pace schedule.
Even in a hot market over a span of two years, per-location costs have actually decreased due to intensive and detailed planning & execution.
15 clinics
27 months
We don’t wait for a final walk-through to address potential issues. This proactive environment means move-in ready stores with few to no submittals, RFI’s or punch list items.
Typical Patient Suite
Designated key contacts at each team partner and vendor were defined early in preconstruction and allowed for long-lead equipment procurement.
60 days / build
“MultiCare developed a new concept in Urgent Care that would better meet the needs of consumers who want easy access to health care services. Andersen Construction was a valuable partner that helped us quickly stand up the Indigo Urgent Care centers with innovative design key to the success of the project. The centers are high quality and inviting and we appreciate the collaborative work that went into building them.”
Christi McCarren, RN, MBA, CPHQ
MultiCare Health System